Johnson Controls, Lučenec
Production Plant Johnson Controls, Lučenec, Piles and heads SO 01, SO 01 – foundation of 12 pcs inner collumns between axes 4 – 5 and F – J, SO 01 – steel extension 1a, 1b, SO 02 – SHZ structure
Client: Johnson Controls
Superior Contractor: ZIPP, spol. s r. o., Bratislava
Construction technology:
Complete execution of pile foundation including monolithic heads.
- reinforced concrete piles D 620 mm 550.4 m
- reinforced concrete piles D 880 mm 448 m
- pile heads 187 pcs
Construction period: June 2005 – July 2005